Apr 01 2025 23 mins 6
The Tennessee Valley Authority (TVA) has for many years been evaluating emerging nuclear technologies, including small modular reactors, as part of technology innovation efforts aimed at developing the energy system of the future. TVA—the largest public power provider in the U.S., serving more than 10 million people in parts of seven states—currently operates seven reactors at three nuclear power plants: Browns Ferry, Sequoyah, and Watts Bar. Meanwhile, it’s also been investing in the exploration of new nuclear technology by pursuing small modular reactors (SMRs) at the Clinch River Nuclear (CRN) site in Tennessee.
“TVA does have a very diverse energy portfolio, including the third-largest nuclear fleet [in the U.S.],” Greg Boerschig, TVA’s vice president for the Clinch River project, said as a guest on The POWER Podcast. “Our nuclear power plants provide about 40% of our electricity generated at TVA. So, this Clinch River project and our new nuclear program is building on a long history of excellence in nuclear at the Tennessee Valley.”
TVA completed an extensive site selection process before choosing the CRN site as the preferred location for its first SMR. The CRN site was originally the site of the Clinch River Breeder Reactor project in the early 1980s. Extensive grading and excavation disturbed approximately 240 acres on the project site before the project was terminated. Upon termination of the project, the site was redressed and returned to an environmentally acceptable condition.
The CRN property is approximately 1,200 acres of land located on the northern bank of the Clinch River arm of the Watts Bar Reservoir in Oak Ridge, Roane County, Tennessee. The CRN site has a number of significant advantages, which include two existing power lines that cross the site, easy access off of Tennessee State Route 58, and the fact that it is a brownfield site previously disturbed and characterized as a part of the Clinch River Breeder Reactor project.
The Oak Ridge area is also noted to have a skilled local workforce, including many people familiar with the complexities of nuclear work. “The community acceptance here is really just phenomenal,” said Boerschig. “The community is very educated and very well informed.”
TVA began exploring advanced nuclear technologies in 2010. In 2016, it submitted an application to the Nuclear Regulatory Commission (NRC) for an Early Site Permit for one or more SMRs with a total combined generating capacity not to exceed 800 MW of electricity for the CRN site. In December 2019, TVA became the first utility in the nation to successfully obtain approval for an Early Site Permit from the NRC to potentially construct and operate SMRs at the site. While the decision to potentially build SMRs is an ongoing discussion as part of the asset strategy for TVA’s future generation portfolio, significant investments have been made in the Clinch River project with the goal of moving it forward.
OPG has a BWRX-300 project well underway at its Darlington New Nuclear Project site in Clarington, Ontario, with construction expected to be complete by the end of 2028. While OPG is developing its project in parallel with the design process, TVA expects to wait for more design maturity before launching its CRN project. “As far as the standard design is concerned, we’re at the same pace, but overall, their project is about two years in front of ours,” said Boerschig. “And that’s by design—they are the lead plant for this effort.”
In the meantime, there are two primary items on TVA’s to-do list. “Right now, the two biggest things that we have on our list are completing the standard design work, and then the construction permit application,” Boerschig said, noting the standard design is “somewhere north of 75% complete” and that TVA’s plan is to submit the construction permit application “sometime around mid-year of this year.”
“TVA does have a very diverse energy portfolio, including the third-largest nuclear fleet [in the U.S.],” Greg Boerschig, TVA’s vice president for the Clinch River project, said as a guest on The POWER Podcast. “Our nuclear power plants provide about 40% of our electricity generated at TVA. So, this Clinch River project and our new nuclear program is building on a long history of excellence in nuclear at the Tennessee Valley.”
TVA completed an extensive site selection process before choosing the CRN site as the preferred location for its first SMR. The CRN site was originally the site of the Clinch River Breeder Reactor project in the early 1980s. Extensive grading and excavation disturbed approximately 240 acres on the project site before the project was terminated. Upon termination of the project, the site was redressed and returned to an environmentally acceptable condition.
The CRN property is approximately 1,200 acres of land located on the northern bank of the Clinch River arm of the Watts Bar Reservoir in Oak Ridge, Roane County, Tennessee. The CRN site has a number of significant advantages, which include two existing power lines that cross the site, easy access off of Tennessee State Route 58, and the fact that it is a brownfield site previously disturbed and characterized as a part of the Clinch River Breeder Reactor project.
The Oak Ridge area is also noted to have a skilled local workforce, including many people familiar with the complexities of nuclear work. “The community acceptance here is really just phenomenal,” said Boerschig. “The community is very educated and very well informed.”
TVA began exploring advanced nuclear technologies in 2010. In 2016, it submitted an application to the Nuclear Regulatory Commission (NRC) for an Early Site Permit for one or more SMRs with a total combined generating capacity not to exceed 800 MW of electricity for the CRN site. In December 2019, TVA became the first utility in the nation to successfully obtain approval for an Early Site Permit from the NRC to potentially construct and operate SMRs at the site. While the decision to potentially build SMRs is an ongoing discussion as part of the asset strategy for TVA’s future generation portfolio, significant investments have been made in the Clinch River project with the goal of moving it forward.
OPG has a BWRX-300 project well underway at its Darlington New Nuclear Project site in Clarington, Ontario, with construction expected to be complete by the end of 2028. While OPG is developing its project in parallel with the design process, TVA expects to wait for more design maturity before launching its CRN project. “As far as the standard design is concerned, we’re at the same pace, but overall, their project is about two years in front of ours,” said Boerschig. “And that’s by design—they are the lead plant for this effort.”
In the meantime, there are two primary items on TVA’s to-do list. “Right now, the two biggest things that we have on our list are completing the standard design work, and then the construction permit application,” Boerschig said, noting the standard design is “somewhere north of 75% complete” and that TVA’s plan is to submit the construction permit application “sometime around mid-year of this year.”